Bagby Street Improvements

Category: Investment Map

Address

300-1200 Bagby St
Houston, TX 77002

View on Google Maps

Details

Through Design Phase I, the Authority worked to analyze the Bagby Street corridor in terms of existing and future traffic conditions such that the Authority can consider future capital improvement projects to reconstruct the roadway and associated infrastructure within the right-of-way. The traffic impact analysis and preliminary engineering study are complete.

Bagby Street Improvement Plan Final Report

The Authority has engaged a civil engineering firm to lead Phase II, project engineering and design. The project will include pedestrian enhancements, beautification elements, the addition of signature lighting and bike facilities, and an upgrade to the corridor‚ storm sewer and drainage system. The design phase is expected to take one year followed by an estimated two-year construction phase.

As a component of this project, the Authority and the City of Houston General Services Department will create a development plan that reimagines the west side of Downtown to better support core civic functions and establishes a framework for future mobility, government, commercial and residential redevelopment.

The total project budget is $28,800,000.

The Authority hosted a Project Open House on Thursday, December 6, 2018, from 5:30-7 PM at the Julia Ideson Building Reading Room. 550 McKinney St, Houston, TX 77002. The presentation can be viewed at the link below.

Bagby Public Open House Presentation

Final design review was presented with area Stakeholders, including proposed phasing plans for construction, this Thursday, September 19, 2019. The Authority is preparing documents for permitting and contract procurement through the fourth quarter. The presentation is available in PDF format below.

Bagby Street Improvement Project Presentation

The project kicks off construction on January 11, 2020 and is expected to be complete in December 2021 (press release).


Project StatusComplete
Year Completed2021
DeveloperDowntown Redevelopment Authority
Asset TypeStreetscape
Investment ($)$28,000,000
DTH+ Investment ($)$28,000,000
DTH+ Funding MechanismCapital Improvement
Funding SourceDRA